Turbine deliveries – 2nd August

On Thursday 2nd August we expect the following turbine component deliveries: 1 lorry arriving at approximately 13:00 *Please note that times are approximate only and are subject to change. The loads will travel down the M1 leaving at Misterton Depot, crossing Wood Farm, then travelling the short distance down Swinford Road to the site entrance at Swinford Corner. […]

Turbine delivery trial run

The latest news onsite from Ian… On 14th May the turbine delivery trial run will take place between 10 and 11 am. This is to ensure that the turbine components can successfully be delivered to the wind farm site ahead of 11th June. Like the turbine component deliveries the lorry will travel down the M1, across Wood […]

Traffic control on Swinford Road

For approximately two weeks from 5th March there will be traffic lights in place along Swinford Road, around 400 metres south of Misterton Grange. Road users can expect short delays during this time and local radio stations will be informed of the works. The works are necessary to construct a track to join Swinford Road […]

Good progress continues onsite

Friday, 20 January, 2012 Since returning to Swinford in the New Year we have made good progress – despite the wet weather. Can’t complain about that too much though really after the long dry spell towards the end of last year! Work is now ongoing at three locations on site. Firstly, to the east of […]

Good progress continues onsite

Friday, 02 December, 2011 Resident Engineer Ian Thomas is delighted with the onsite progress so far… While we may only have been onsite for a few weeks, so much has already happened that it seems as if we’ve been here a lot longer! Since work began, we’ve laid approximately 2120 metres of track that will […]

Images on Flickr

aadn Community Fund Launch. Guess the number of balloons.aadq Community Fund Launch. Wind mills and wind turbines.aadt Community Fund Launch. Diablo!aadp Community Fund Launch. Activities.aadu Community Fund Launch. Touching a turbineaadr Community Fund Launch. Pedal power!aado Community Fund Launch. Giant Jenga!aads Community Fund Launch. Activities.aaea Community Fund Launch. Tug o waraaeb Community Fund Launch. The view from South Kilworth Village Hallaadx Community Fund Launch. Piers Guy announcing turbine name winnersaadw Community Fund Launch. Ring around a turbine.aadv Community Fund Launch. Touching a turbineaadz Community Fund Launch. Eight Parishes CIC receiving their first year of fundingaady Community Fund Launch. Harvey Everton, overall winner of the turbine naming compaadd Construction almost completeaada Youth Focus Group look inside a bladeaacy Youth Focus Group girls enjoy a picnic onsiteaadc The wind farm taking shapeaacz Youth Focus Group learn about wind farm construction