June 2012

Turbine installations off to a good start

This week has seen significant progress with the start of the installation of base and mid tower sections.   There are two cranes onsite lifting the tower sections. The process starts with a “top and tail” lift, where both cranes lift the tower section until it reaches an upright position. Then, the smaller crane releases, […]

Turbine deliveries – 2nd July

On Monday 2nd July we expect the following turbine component deliveries: 1 convoy of 2 lorries arriving at approximately 07:30 am 1 convoy of 3 lorries arriving at approximately 12:30 pm (this convoy marks the end of the blade deliveries- with all 33 blades now sitting on the blade fingers at each turbine location ready to be installed week […]

Turbine deliveries – 29th June

On Friday 29th June we expect the following turbine component deliveries: •1 delivery convoy of 3 lorries arriving between approximately 12:00 – 12:30 pm. •1 delivery lorry arriving between approximately 13:00 – 13:30 pm. *Please note that times are approximate only and are subject to change. The loads will travel down the M1 leaving at Misterton Depot, crossing Wood […]

Turbine deliveries – 28th June

On Thursday 28th June we expect the following turbine component deliveries: •1 delivery convoy of 2 lorries arriving at approximately 07:30am. •1 delivery convoy of 3 lorries arriving at approximately 12:30pm. •1 delivery lorry arriving at approximately 13:30pm. *Please note that times are approximate only and are subject to change. The loads will travel down […]

Turbine deliveries – 27th June

On Wednesday 27th June we expect the following turbine component deliveries: •1 delivery convoy of 2 lorries arriving at approximately 07:30am. •1 delivery convoy of 3 lorries arriving at approximately 12:30pm. •1 delivery lorry arriving at approximately 13:30pm. *Please note that times are approximate only and are subject to change. The loads will travel down the M1 […]

Images on Flickr

aadn Community Fund Launch. Guess the number of balloons.aadq Community Fund Launch. Wind mills and wind turbines.aadt Community Fund Launch. Diablo!aadp Community Fund Launch. Activities.aadu Community Fund Launch. Touching a turbineaadr Community Fund Launch. Pedal power!aado Community Fund Launch. Giant Jenga!aads Community Fund Launch. Activities.aaea Community Fund Launch. Tug o waraaeb Community Fund Launch. The view from South Kilworth Village Hallaadx Community Fund Launch. Piers Guy announcing turbine name winnersaadw Community Fund Launch. Ring around a turbine.aadv Community Fund Launch. Touching a turbineaadz Community Fund Launch. Eight Parishes CIC receiving their first year of fundingaady Community Fund Launch. Harvey Everton, overall winner of the turbine naming compaadd Construction almost completeaada Youth Focus Group look inside a bladeaacy Youth Focus Group girls enjoy a picnic onsiteaadc The wind farm taking shapeaacz Youth Focus Group learn about wind farm construction