A newsletter will be sent to all local homes shortly. It will provide details of: The upcoming turbine deliveries and installations schedule The Community Fund open events in June and how you can have your say Progress on site to date Information points for local residents during the turbine installation phase

Turbine deliveries and installations

The dates for the turbine deliveries and installations has changed. We now expect to begin turbine deliveries on 18th June and turbine installations on 16th July. More information on the whole process is included in the next newsletter which will be sent to all local homes shortly.

Permanent met mast is successfully installed

The permanent met mast was installed onsite today. At 80 metres in height the met mast is the first structure visible in the skyline ahead of the turbines, which we will start installing in July. We will be sending out a newsletter to all local homes detailing the turbine delivery and erection process in the […]

Turbine delivery trial run is a success!

The turbine delivery trial run went ahead today and we are pleased to say that it was a success. The lorry followed the planned route, leaving the M1 at Misterton Depot, crossing Wood Farm and then taking Swinford Road to the site entrance. There are a couple of areas onsite where we will make slight […]

Turbine delivery trial run

The latest news onsite from Ian… On 14th May the turbine delivery trial run will take place between 10 and 11 am. This is to ensure that the turbine components can successfully be delivered to the wind farm site ahead of 11th June. Like the turbine component deliveries the lorry will travel down the M1, across Wood […]

Images on Flickr

aadn Community Fund Launch. Guess the number of balloons.aadq Community Fund Launch. Wind mills and wind turbines.aadt Community Fund Launch. Diablo!aadp Community Fund Launch. Activities.aadu Community Fund Launch. Touching a turbineaadr Community Fund Launch. Pedal power!aado Community Fund Launch. Giant Jenga!aads Community Fund Launch. Activities.aaea Community Fund Launch. Tug o waraaeb Community Fund Launch. The view from South Kilworth Village Hallaadx Community Fund Launch. Piers Guy announcing turbine name winnersaadw Community Fund Launch. Ring around a turbine.aadv Community Fund Launch. Touching a turbineaadz Community Fund Launch. Eight Parishes CIC receiving their first year of fundingaady Community Fund Launch. Harvey Everton, overall winner of the turbine naming compaadd Construction almost completeaada Youth Focus Group look inside a bladeaacy Youth Focus Group girls enjoy a picnic onsiteaadc The wind farm taking shapeaacz Youth Focus Group learn about wind farm construction