First details of turbine deliveries

We now have the early provisional details of the turbine delivery and erection schedule from the turbine suppliers Vestas. The programme is still developing, and we are still awaiting some key information (e.g. the timings of the turbine delivery). We can now confirm that the turbine delivery trial run will take place on 14th May. We expect […]

Schools flag project off to a flying start

The school project got off to a flying start last week at South Kilworth Primary School with the first of the art workshops. The session was led by the artist Lucy Birbeck, who brought images and photographs on theme of the weather and climate to inspire the children. Below are some examples of the brilliant work completed […]

Schools project starts next week…

With the core foundation works now close to completion on site, we are gearing up towards the arrival of the turbines in June. This starts next week when a flag project will start with Swinford and South Kilworth Primary Schools. During April and May, pupils will be taking part in art workshops on the theme […]

All concrete work now complete

Ian’s back and raring to go! We have hit the ground running after a well earned Easter Break. The two remaining upstand sections have now had their concrete poured, which means that all concrete works onsite are now complete. The turbine foundations are ready for the turbines. All that is left to do around the turbine bases is […]

Public rights of way updates

Through careful management, we have been able to keep all public rights of way onsite open during construction. Health and safety is our most important consideration at all times, and the team are given regular health and safety briefings to reinforce key measures such as keeping to the onsite speed limit of 15mph, and taking care […]

Images on Flickr

aadn Community Fund Launch. Guess the number of balloons.aadq Community Fund Launch. Wind mills and wind turbines.aadt Community Fund Launch. Diablo!aadp Community Fund Launch. Activities.aadu Community Fund Launch. Touching a turbineaadr Community Fund Launch. Pedal power!aado Community Fund Launch. Giant Jenga!aads Community Fund Launch. Activities.aaea Community Fund Launch. Tug o waraaeb Community Fund Launch. The view from South Kilworth Village Hallaadx Community Fund Launch. Piers Guy announcing turbine name winnersaadw Community Fund Launch. Ring around a turbine.aadv Community Fund Launch. Touching a turbineaadz Community Fund Launch. Eight Parishes CIC receiving their first year of fundingaady Community Fund Launch. Harvey Everton, overall winner of the turbine naming compaadd Construction almost completeaada Youth Focus Group look inside a bladeaacy Youth Focus Group girls enjoy a picnic onsiteaadc The wind farm taking shapeaacz Youth Focus Group learn about wind farm construction